image_pdfimage_print

Falling electricity demand and the impact on nuclear projects

During the summer I have been a slacker when it comes to contributing to my blog.  It is a time for relaxation; a good time for reading and reflection.   

As we all start the big climb out of the current economic crisis, it may be time to start thinking about what lies ahead and the legacy that this crisis will have left us.  There has been an assessment by the IEA in May about the impact of the financial crisis on energy in general and a more detailed assessment of nuclear power in the USA by Moody’s in June.  So why am I thinking of talking about this now in August?

Well, this week OPG (Ontario Power Generation) announced their second quarter results here in Ontario Canada (home for me).  They reported a 19% drop in electricity production for the second quarter.  In part this is due to lower overall demand and also is related to production by others in the market.   Now there are a number of reasons for this lower demand.  First and foremost, this has been a mild summer so the air conditioning loads are down.  Second the economy has had a big effect on industrial loads and finally, the success of the OPA conservation programs is starting to show benefits in the market.

This summer has seen some unusual things happen in the Ontario market.  Nuclear plants have had to be shut down due to the lack of load.  This is a result of low off peak demand and an increasing amount of renewables on the system that displace base load when the resource is available according to electricity market rules.  Also this summer, the government of Ontario suspended its bidding process for a new build nuclear plant.  The reasons given were the high cost of the bid and the uncertainty over the future of AECL, the lead bidder.   AECL’s shareholder; the Government of Canada, is looking to partially privatize the national nuclear vendor.  I would guess that the lower demand probably also had an impact.  Hard to think about spending large amounts of capital when demand is shrinking. 

In any case, reading about OPG made me think so I have had a look at the numbers.  Demand has decreased in Ontario since 2005.  Current projections by the IESO are for a 4% drop in demand this year and a further 0.35 drop next year.  Wow!  A far cry from even the modest 1% or so growth assumed in the current Integrated Power System Plan.  This is consistent with the IEA forecasts.  They are expecting a drop of 3.5% in 2009; the first drop in global electricity demand since the second world war!

The Moody’s report is more focused and suggests that US utilities that are considering new nuclear plants are not doing what is necessary to strengthen their balance sheets to get ready for these large projects.   Moody’s claims that the size of these projects makes them “bet the farm” projects – a term I often use when teaching project structuring for the World Nuclear University.  However, they also note on the positive side that there is a demand for new low carbon generation and that nuclear as an economic alternative can play a role.

So what does this mean for the future of nuclear in North America?  The IEA is somewhat negative and states that the crisis may hold back some programs.  It mentions South Africa as an example of one country that has delayed its new build projects for financial reasons.  On the other hand, it also states that nuclear is probably the only large scale viable low carbon generation option and that its economics improve as carbon is priced.  They also note that most programs that are in the advanced planning stages are continuing and once operating nuclear plants are viewed favourably by the financial community.

To answer the question – the current economic climate may delay some new nuclear projects, however it is expected that most will continue and that they will be able to raise the necessary financing as the economy starts to improve.   Most likely, investor-owned utilities in North America will look to strategic partnerships to share costs and risks.  The lower demand may also buy the industry some time to ensure that it plans and executes new projects with the necessary diligence and oversight to ensure project success.  Given the relatively high capital costs and long project schedules of a nuclear plant, projects currently in the preparation phase will be in service towards the end of the decade.  And of course, continued focus on implementing new projects on budget and on schedule will be key to a successful future.

MIT Report Update “The Future of Nuclear Power”

This week MIT released an update to its 2003 report, “The Future of Nuclear Power”.  Back in 2003 this report brought the economics of nuclear power in the United States to the forefront.  It supported new nuclear as a low carbon option for electricity generation and considered a scenario that would see the increase in capacity by a factor of 3 (meaning building about 200 new units) by the middle of this century.  It is commonly accepted that this report was an important input into the policy that followed with respect to nuclear power including the nuclear power 2010 program and the Energy Policy Act of 2005.

This update looks at progress over the past 6 years and of most interest, updates the economics.  The following table from the report shows the new versus old analysis.

Click on table to enlarge

Click on table to enlarge

As can be seen, the costs have increased significantly over this time period with the projected costs of nuclear increasing faster than the costs of the coal and gas alternatives.  However, the authors draw the same conclusions as they did in 2003; that nuclear is competitive with the alternatives. The report continues to assume a higher project risk for nuclear than fossil.  This translates into a higher cost of capital and the highest cost of electricity.  Assuming the same cost of capital as the alternatives results in nuclear being extremely competitive.

I want to comment on the costs and assumptions.  I have to admit, that back in 2003, when I worked for a nuclear vendor, I was not happy with this report assuming nuclear at $2,000 /kW.  At that time we all believed that we were making strides to lower the cost of new plants and we wanted to see that reflected in the analysis.  Well, I was wrong.  Today the cost of nuclear power has increased and I do accept that $4,000 /kW is a reasonable assumption to make in today’s world.  Does that mean that I think that it is OK for nuclear plants to cost $4,000 /kW?  I definitely think that more work needs to be done to bring these costs down but that is the subject for another discussion.

On the other hand, things have evolved so that the other assumptions do need to be challenged.   While it may have made sense to assume different costs of capital in 2003, this is no longer the case.  The argument in the report is based on the industry’s poor track record of building on time and on budget.  It states that issues with new plants since that date confirm this and that the risk premium can only be eliminated with proven plant delivery performance.  While I do agree that the industry needs to prove it can deliver a new fleet of plants to budget and schedule, things have changed since 2003.

In the current environment, the majority of new plants under consideration in the United States are with regulated utilities.  These plants will be financed on balance sheet so they will be financed at the cost of capital of the utility itself, no different than if it were to build a coal or a gas plant.  And now that the cost estimates have escalated significantly, it is reasonable to assume that part of this increase is due to utilities being more conservative and taking the risks into account in the cost estimates themselves.

Also, the risks of the alternatives have changed significantly.  The risk of new climate change initiatives being put into place after the coal or gas plant is committed has increased.  This means additional costs to the utilities to implement new carbon control requirements or charges due to additional costs for releasing carbon are likely.  Is $25/t sufficient?  At this stage nobody knows meaning higher risk.

And finally, it is interesting how the success of carbon capture and storage (CCS) is assumed, even though the technology has yet to be demonstrated while the success of building a new nuclear plant is consistently challenged.  The MIT study itself recognizes that CCS is not proven. The costs of CCS seem to go up every time a new estimate is made, yet they assume that nuclear has a higher risk profile and cost of capital than coal with a yet to be proven technology attached to it.

In the case of a merchant plant, should there be one; it will very likely only be implemented under the US government loan guarantee program.  This means that they can achieve the 80/20 debt/equity ratio assumed for the other technologies with even a lower potential cost due to the benefit of the government guarantee.

All that being said, the timing of this update is useful.  Their conclusion that more needs to be done is important.  As stated “The sober warning is that if more is not done, nuclear power will diminish as a practical and timely option for deployment at a scale that would constitute a material contribution to climate change risk mitigation.” It will be interesting to see how both government and industry respond.